by Jonathan McGaha | 31 August 2016 12:00 am

Burk Erectors Inc. erected Ceco Metal Building Systems’ metal building system for Inergy LP’s propane manufacturing facility. The 68,000-square-foot building has an approximately 40-foot eave height, metal roof decking with 4-inch board insulation and Thermal Design Inc.’s 6-inch Simple Saver System insulation in the walls. It was completed in December 2014. The Metal Building Contractors and Erectors Association gave the project its 2015 Award of Excellence in the manufacturing category.
General contractor: Miller Stauch Construction Co., Kansas City, Kan.[1]
Erector: Burk Erectors Inc., Battlefield, Mo.[2]
Insulation: Thermal Design Inc., Stoughton, Wis., www.thermaldesign.com[3]
Metal building system: Ceco Metal Building Systems, Columbus, Miss., www.cecobuildings.com[4]