If an expansion project were to be scripted and turned into a Hollywood movie, then a fantastic candidate for the big screen would be the 82,500-sf expansion of Feldmeier Equipment’s headquarters in Syracuse, N.Y., in 2025, carried out by design-builder VIP Structures.
This is a story of an expanding expansion, a whole new structure, roads and truck traffic, crane action … not only does this story have it all, but it also comes with a happy ending.
Spoiler alert! The project was a category winner in the 2026 Varco Pruden Hall of Fame Awards and recently received a Construction Excellence Award from Associated Builders and Contractors (Empire State Chapter).
No stranger to the winners’ circle, this project marks the 24th time one of VIP’s industrial projects has been honored by VP’s builder network recognition program—including a Best of Category win for the original Feldmeier facility in 2019.
The Feldmeier Syracuse backstory
The expansion story actually started about 10 years ago when Feldmeier—a manufacturer of stainless steel processing equipment for industries such as pharmaceutical and food & beverage—first built its 125,000-sf facility in Syracuse, which consolidated the owner’s local operations while establishing the building and site for continued growth.
VIP Structures served as the design-builder at that time. The facility included a PEMB manufacturing area and a conventional steel administrative wing. It included 8-in. reinforced concrete floors, overhead bridge cranes, and a specialized structural system to support the fabrication of large tanks.
“The main part of the manufacturing area is clad with insulated metal panels in a variety of colors,” explained Tom Malinowski, senior project architect at VIP Architectural Associates of Syracuse during that first build.
“The office portion of the building is clad in ACM, glass, concrete veneer, and IMPs [which] offered us a variety of colors as well as the capability to match Feldmeier colors. We were also able to achieve the desired R-value for the facility, saving the owners on heating and cooling costs.”
More than 56,600 square feet of insulated metal panels from Metl-Span were installed on the building. Almost 36,000 square feet were CF 36 Striated panels in Polar White with another 9,600 square feet in Slate Gray.
CF 7.2 Insul-Rib panels were installed as accent panels—some in Tundra, some in Regal Blue. About 2,600 square feet of the CF 42 Striated panels in Tundra were also installed. The IMPs were all 2.5-in. thick with interior panels in Igloo White.
Baked into this original facility—which was completed in 2018—was the decision to plan ahead for possible future expansion.
2024 brings the sequel to the prequel
As the business grew, Feldmeier Equipment realized it needed more space. The future had arrived. VIP Structures came aboard again as the design-builder.
Their job? Expand the manufacturing facility to the south without stopping production, keep the trucks coming and going, work around equipment on the production floor, and accommodate the two-shift operation inside.

“The original building was designed to be expanded along the south edge for an extension of 65 feet. And the frames along that sidewall were all designed to carry the additional load,” explained Tom Malinowski, who served as VIP project architect for the expansion. “And because of the use of cranes within the facility, those sidewall columns also were designed to handle an additional crane load, essentially equal to what it was handling on the other side.”
But as these things often do, the project scope changed, which VIP took in stride. The owner decided to make the addition larger overall—almost double the size of the initial expansion plan. “Everything was set up for a 60-ft addition, and they said they would like to push it further,” recalled Jim Herr, vice president, construction, with VIP.
Because the building runs parallel to the New York State Thruway, there was only so far the expansion could be stretched, Herr said. Still, the perimeter road had to be moved, along with the swale.
“As we pushed closer to the edge of the property line, the grade was so steep that we had to add a retaining wall to be able to make the grade change there,” Herr said. “The work blossomed into a much bigger addition than what they originally planned.”
And if that wasn’t enough of a curve ball, another soon followed: a new 10,000-sf standalone building for stock and storage on the north side.
“The original planned expansion along the south wall totaled about 39,000 square feet. And the final total of the two additions was about 80,000 square feet, so the project more than doubled,” said Malinowski.
Complicating the site was the regular truck traffic.
“They had trucks constantly—three, four, five times a day—that would show up with raw materials or to ship things out,” said VIP construction project manager & director of field operations Cody Hoose.
“It’s a pretty active truck way, so the design was created in such a way that access could be maintained during construction as well as possible,” Herr agreed.

Because of this, a new roadway was installed early in the project to maintain access for regular truck traffic, construction activity, and emergency vehicles. As the work progressed, the teams continued planning around incoming materials, outgoing products, and daily site movement so the plant could remain functional while construction continued.
A tolerance for cranes … and open walls
The expansion was built using Varco Pruden PEMB systems, the same used in the original facility. This required coordination between VIP’s Architecture and Construction teams and Varco Pruden to align the new structure with the existing building across a 600-ft span.
“Varco Pruden did the structural design, but VIP was responsible for an accurate foundation,” Malinowski said. “I think the biggest challenge was coordinating with VP for the east end where the expansion extended 100 feet beyond the existing building. We had to dimensionally offset a column with a bracket relative to the existing building’s columns and brackets to ensure the alignment of the crane rail. From a design coordination, structural standpoint, that was the biggest thing.”
The extensive overhead crane system really stands out in this expansion project—five 10-ton cranes and one 15-ton crane on the north side, and three 5-ton cranes on the south side.
Complicating matters and reinforcing the need to work closely with the PEMB provider was the fact that the existing IMPs on the building had to stay in place, said Hoose. “It changed the depth of where the crane stub columns had to be welded to the existing columns, which had to hold a 6-inch tolerance from the face of the IMP to the edge of the crane. This required extensive collaboration with the Varco Pruden engineers to hold this tolerance.”
When the metal building system from Varco Pruden showed up, it came with crane stub columns that were welded onto the new columns, which served as VIP’s “zero,” Hoose explained.
“We would make sure those were level across to where we had to weld the new crane stub columns on,” Hoose continued. And to make this happen, the existing south wall had to be cut open, then closed again after the crane work.
“As soon as we would tack-weld one of them on, we would check it to make sure it was within line. After it was fully welded, we checked it again,” Hoose recalled. “And after all of them were pretty much done, we had everybody go back and triple- and quadruple-check them.”
“It starts at the anchor bolts, basically, of the columns. They’ve got to make sure those are really accurate and at the correct elevation. And then you can work your way up to the brackets themselves that are 25 feet in the air, then start to get those located properly. And it worked out well. The cranes fit and run really well,” said Herr.
Across that 600-ft span, VIP’s field team installed crane rail brackets within a 1/4-in. tolerance. Using laser verification and multiple checks, most locations landed within 1/8-in. or 3/16-in. of target, Hoose confirmed.
The north takes priority
Back in 2018, the original expansion concept anticipated about 39,000 square feet on the south side of the building but, as we’ve already learned, that need had multiplied by the time Feldmeier was ready to move forward. And then there was the additional north building.
“The project started with the owner wanting the south addition done as quickly as possible. And then, all of a sudden, the north addition was the most important,” Malinowski said.
The project team shifted focus. The steel erector redeployed from the south addition to the north and subcontractors adjusted their work.
“Yes, it was a change, but our subcontractors worked really well with us. We brought it up to them immediately, and then everybody shifted gears and got going and delivered the north addition, 10,000 square feet, about two months early,” said Hoose.
Opening and closing the building
Because the original facility had been designed with expansion in mind, VIP could tie the south addition into the existing structure without adding new building columns along the connection line.
Tie-in work required careful coordination at the existing insulated metal panel wall and around the building envelope.
The new steel connections high up on the eave of the building were an important consideration, said Herr. VIP had to cut as small an opening as possible to be able to fit the rafter and weld the brackets and additional plates onto the existing columns so they could be neatly trimmed out later. They were not going to remove the existing insulated metal panel walls, so it was vital to plan those openings properly and cut the smallest sized holes possible.

VIP cut only the openings needed to make steel connections and kept larger wall openings closed until the new addition was enclosed. Temporary openings were sealed with plastic and tape to help prevent water infiltration. Existing gutters remained in place as long as possible, and temporary piping was used where needed to direct roof runoff away from work areas.
“Then we were able to enclose the building before we really started making any of the larger openings for, say, forklift traffic or product flow between buildings,” Herr said. “And when we took off the overhead door, we would still try to keep the building enclosed as much as we could, because a lot of the work we were doing was in the winter time.”
“The biggest thing was making sure that the existing facility was always secure. We didn’t open any of the existing wall openings low, and nothing at grade until we were fully closed in—doors in, overhead doors on,” Hoose added.
The extension was built just slightly lower than the existing building, Herr explained, so careful attention was paid to managing that drop by keeping gutters in place and running some temporary piping to direct the outflow of water.
“When they designed the new addition, that snow drift that would be coming onto the new building was an important consideration,” said Hoose. “And Varco Pruden did a great job with the design, and we made sure that the column locations and the actual foundations were correct before we started putting up the steel columns.”
“Regarding the attachment of IMPs and larger openings … we had one at floor level that was 16 by 20 feet. We had to add new framing to the existing wall, vertical C-sections to create those openings, and then trim them out,” Hoose added.
Hoose credits having the correct tools and doing things the right way for the flawless integration of new and old IMPs. “The team did a really nice job cutting the opening only to the size that we needed, not overcutting or having an issue with the seams.”
In all, 34,300 square feet of IMPs from Metl-Span were installed for the south extension and 9,050 square feet for the north addition.
When asked how the new IMPs stacked up against the existing panels, Malinowski didn’t really notice any real difference in colors, and Herr enthusiastically chimed in that the color match came out really well.
Communicating in the now, and for the future
The Feldmeier facility runs two shifts, with trucks always going in and coming out. So how did VIP execute the project without tripping over the owner’s operations?
“We had a weekly meeting with the client, and our superintendent was always communicating with their operations manager,” Hoose explained. In those meetings, they would review schedules and truck deliveries—even if they were three weeks away.
For work inside the facility, Hoose tipped his hat to VIP’s superintendent, who did “a very nice job” of letting the owner know in which areas VIP would be working, especially along the south wall of the existing building, where numerous pieces of equipment are located.
And VIP remained flexible in case scheduled work or a particular location impacted Feldmeier’s operations.
“You let us know if we can’t be in there, and we’ll jump to a different column or a different bay,” Hoose said. “We did that a couple of times to help them keep their operation running. It came down to a lot of coordination and back and forth. The goal was to hit our scheduled completion date to turn the building over, and the client worked very well with us. It was very smooth in terms of coordinating the work around the existing facility.”
An important point to this story is the role the builder plays in helping clients look ahead and see themselves five, 10 or 15 years from now. Herr believes that planning for the possibility of future expansion is an important conversation to have with any owner regarding their new facility—especially if it is their first.
“We’ve worked with so many clients over our 50 year history, and we’ve got many that have already gone through two, three, four, five additions—even more,” Herr said. “Those just starting out don’t even want to think about adding on, but we try to get them thinking about that possibility and plan for it. Some things, like loading docks, are very hard, very expensive to move.”
Although the plot line changed a few times over the course of the Feldmeier expansion project, the story came to a successful conclusion, thanks to its star-studded blend of imagination, ingenuity, and adaptability, constant communication, and strong collaboration … not to mention meticulous measurements.
Anthony Capkun is the editor-in-chief of Metal Construction News and Metal Architecture magazines. Raised as a drywaller, he has spent over two decades as an editor in the construction sector.